Expected Site Timeline
01.
September 2023
Site preparations start.
02.
December 2023
Tophole drilling.
03.
February 2024
Drilling of two test wells
04.
June 2024
Analysing test results, adjustments and the first geothermal plant is built.
05.
Autumn 2025
First heat to be delivered from the facility.