Project: Aarhus, Skejby

In Skejby, we are building the first of a total of seven facilities

Site preparations in Skejby began in September 2023, marking the initial phase of the project where we prepare the site for the drilling operations. The drilling will be carried out in the early months of 2024, and then construction of the heating plant will start.

The facility is expected to deliver the first heat to the citizens of Aarhus in 2025.

Expected Site Timeline

01.

September 2023

Site preparations start.

02.

December 2023

Tophole drilling.

03.

February 2024

Drilling of two test wells

04.

June 2024

Analysing test results, adjustments and the first geothermal plant is built.

05.

Autumn 2025

First heat to be delivered from the facility.

Explore Our Skejby Site