Expected Site Timeline
01.
September 2023
Site preparations start.
02.
December 2023 - January 2024
Tophole drilling.
03.
February – May 2024
Drilling of two test wells
04.
June 2024 – Summer 2025
Analysing test results, adjustments and the first geothermal plant is built.
05.
Autumn 2025
First heat to be delivered from the facility.