In Skejby, we have built the first geothermal facility in Aarhus

Site preparations at Skejby began in September 2023, followed by the drilling of two test wells in the early months of 2024. Construction was completed in 2025, and the Skejby facility delivered its first geothermal heat to homes in Aarhus in late October.

By 2027, two additional wells are expected to be drilled to further increase the capacity.

Expected Site Timeline

01.

September 2023

Site preparations start.

02.

December 2023

Tophole drilling.

03.

February 2024

Drilling of two test wells.

04.

June 2024

Analysing test results, adjustments and the first geothermal plant is built.

05.

October 2025

First heat delivered from the facility.

06.

Fall 2027

Drilling of two additional wells is expected to begin.