Project: Aarhus, Sumatravej

At the Port of Aarhus we are building one of a total of seven heating facilities

At the Port of Aarhus, site preparations began in April 2023. Come September, the water well rig arrived to commence drilling the tophole for the first well. In November, we commenced the drilling operation of the very first well.

The heating facility at the Port of Aarhus is projected to reach completion by 2027.

Expected site timeline

01.

April 2023

Site preparations begin.

02.

September 2023

Tophole drilling.

03.

November 2023

Drilling of well 1.

04.

Winter 2025

Drilling of well 2 and 3.

05.

February 2026

Construction of heating facility begins.

06.

2027

First heat to be delivered by the facility.